Tillicum School Seismic Upgrade
The project consisted of the addition of both internal and external structural steel to fortify the existing structure, in conjunction with reinforcement of the masonry block components of the school. This project required complex phasing of the schedule in order to complete all aspects of the work in the time frame that was allotted without interrupting any classroom activities throughout the school year. The major structural work required inside the classrooms was carried out over two summers, using a compressed schedule, with selective demolition to prepare for this work being carried out during the school year.